As a major artery and vital piece of infrastructure within the centre of Leeds, Woodhouse Tunnel - which carries the A58(M) beneath the busy city centre and Leeds General Infirmary, as well as adjacent to the university – sees over 75,000 cars pass through every day.
Undertaking over 400 nightshifts within a two year period, we provided a wide breadth of specialist trades, fixing over 500 tonnes of reinforced steel, placing over 5000m2 of formwork and pumping nearly 2000m3 of concrete.
Expert planning and logistics were taken into consideration as the removal of traffic control processes would have resulted in rush hour gridlock throughout Leeds’ main highways network. Traffic management was implemented at key strategic points of the day to minimise any traffic disruption.
Contract Value
Confidential
Scope
- Ground Works
- Hydro-demolition
- Waterproofing
- Cathodic protection
- Concrete repair
- Drilling
- Formwork
- Reinforcement
- Resin Anchoring
- Footpath Construction
- Lighting Foundations